School building cost calculator

Estimate a UK school capital project end-to-end: works at BCIS Q2 2026 £/m² with regional factors, plus Spec21 net zero, BNG, FF&E, professional fees and abnormals. Outputs a CIF Section C ledger and £/pupil place.
Estimator inputs
Uplifts
CIF Section C

Cost summary (preview)

GIFA (DfE BB103 area calc)2,856[BB103]
Works at £/m² (BCIS Q2 2026 × East of England 1.00)£2,415[BCIS Q2 2026]
Sub-total works£6,897,240[LGA Bench.]
+ Net Zero Spec21 (+10%)£689,724[Spec21]
+ FF&E (8% of works)£551,779[LGA p.42]
+ Professional fees (10%)£689,724[CIF 2026-27]
+ Abnormals (5% allowance)£344,862[NAO Jan 2025]
ALL-IN SCHEME COST£9,173,329audit
£/m² all-in£3,212derived
£/pupil place£21,841derived
LGA Bench. 2024 · primary
Median to Q3 (above market)
Q1 £2,600Median £3,200Q3 £3,650Outlier £4,150
Your figure: £3,212/m²

How the calculator builds the figure

The estimator derives GIFA from your pupil count using BB103 for mainstream and BB104 for SEN[BB103][BB104]. It applies a BCIS Q2 2026 base £/m²[BCIS Q2 2026], multiplies by the BCIS regional location factor for your area, then layers project-type and method multipliers (refurbishment is materially lower per m² than new-build; volumetric modular trims around 4% off the headline rate but the larger benefit is programme certainty).

Uplifts are configurable. Net Zero Spec21 adds 10% to works in line with DfE's 2024 output specification[Spec21]. BNG adds around 1.5% on a typical school site. FF&E sits at 8% of works as a planning figure; ESFA caps consultant fees at 10% of works under CIF 2026-27[CIF]. The default abnormal allowance is 5%; raise it where asbestos, RAAC[RAAC] or contaminated land is known.

What is excluded

The calculator is a planning anchor, not a tender estimate. It excludes site acquisition, statutory fees outside the ESFA cap (planning, building control, BNG off-site units), VAT recovery rules, finance costs and inflation beyond the BCIS quarter loaded. For tender-stage certainty, instruct a chartered QS and price against the live design.

Calculator math (worked example)

A 2FE primary (420 places) at England-average region with Net Zero, FF&E, fees and abnormals on: GIFA = 420 × 6.8 m² = 2,856 m². Works rate = £2,415 × 1.00 = £2,415/m². Sub-total works = £6,897,240. +Net Zero 10% (£689,724), +FF&E 8% (£551,779), +Fees 10% (£689,724), +Abnormals 5% (£344,862). All-in: £9,173,329. £/m² all-in: £3,212. £/pupil place: £21,841. The on-page calculator will reproduce these to within rounding.

For loaded scenarios with worked examples, see archetypes or jump straight to a preset: 2FE primary, 6FE secondary, SEN 60-place, modular new-build, refurbishment.